Five workstreams over roughly fourteen weeks. Most of it is standard launch work — but two items are net-new product builds, and they sit on the critical path. Track progress below; it saves to this browser.
Bars show each workstream's span. Outlined bars and red milestones mark the critical path — the chain that actually gates go-live.
Estimates are indicative for planning — sequence is firmer than the absolute durations.
Tick items as they land. Progress persists in this browser so you can come back to it.
margins, tiers, uptime/SLA, endpoint counts, NPS
get written usage rights
Northstar / Metro Civic or replacements
replace stock placeholders
both partner and direct sites
privacy, cookies, terms, partner agreement, a11y, VPAT
Vite / Next — browser compile is not production-grade
currently Google Fonts CDN — perf/privacy/GDPR
Safari, Firefox, Edge, Chrome
keyboard nav, focus, alt text, contrast, SR labels
titles/meta, OG cards, favicons, sitemap, robots, schema
image optimization, lazy-load, Lighthouse
HubSpot / Salesforce / Marketo or form service
internal alert + applicant confirmation
captcha/honeypot
reviewer queue → approval → credential issuance
not a mockup — actual auth
data processing records
biggest hidden lift — start week one
the core partner promise
tier gating
attainment, rebates
newsco.com, /partners, partners.newsco.com
GA4 / Plausible
policies, partner agreement, claims
esp. public-sector compliance claims
margins, tiers, approval policy
The marketing pages can ship early. What you can't fake is the partner approval flow and the portal it unlocks — those are real authenticated product, not page design. Scope the portal as its own project and start it in week one; everything else can flow around it.